Well, here is the list of things that did not come off as planned…
1. Xerox plotter blew the power supply - down time - 2 days
2. DHCP was not handing out IP addresses correctly to some stations - downtime - 30 minutes
3. Some users not mapping correctly, error in the login script - edits we made - downtime - 30 minutes
4. Server not recognized by some stations - reboot - downtime - 15 minutes
5. Employee fingerprint scanner access to the building - blown power supplies - downtime - 4 days
6. Toilets in the building back up into the kitchen - whole building with no toilets - half day.
So some things you can plan for and some you cannot.